The Department is delivering the Norfolk Island Kingston Pier Channel Construction Project (the Project) to improve maritime safety and access at Kingston Pier, while respecting the area’s environmental and heritage values.
Kingston Pier is a critical piece of infrastructure for Norfolk Island, supporting cargo operations, emergency services, fishing activities and passenger transfers. The existing navigation channel leading to the pier has limited depth and manoeuvring space at lower tides, which can restrict access and pose safety risks for vessel operators. The pier structure also requires maintenance to ensure it remains safe and fit for purpose.
The rock revetment wall to the west requires repair and an extension to respond to the expected changed wave action due to the deeper channel and this is planned to occur prior to the dredging and pier repair work.
Project objectives
The key objectives of the Project are to:
- improve maritime safety by providing a deeper and wider navigation channel for commercial and recreational vessels
- increase the availability of Kingston Pier for berthing by providing a safer approach for vessels
- ensure the Project is consistent with the Kingston and Arthur’s Vale Historic Area Heritage Management Plan
- consider and minimise environmental, social and economic impacts
- keep the community and stakeholders informed and involved in key decisions
- allow for potential future access by larger vessels
Community involvement
The Norfolk Island community has played an important role in the development of the Project. Community feedback has informed the design and helped shape the final approach to improve safety and functionality while protecting the local environment and heritage values.
Project scope
The Project involves:
- deepening the navigation channel to approximately 3.2 metres below mean sea level
- widening the navigation channel and vessel turning area to improve manoeuvring
- dredging approximately 4,700 cubic metres of material
- transporting dredged material to Cascade Quarry for beneficial reuse as part of quarry restoration works
- screening dredged material for archaeological artefacts
- minor remediation works to the pier, including repairs to steel sheet piling and replacement of timber fenders
- additional concrete strengthening works to support the deeper channel
- installation of a new navigation aid to improve vessel guidance
Environmental approvals
The Project was assessed under the Environment Protection and Biodiversity Conservation Act 1999. It was determined to be a controlled action and required assessment through a Public Environment Report.
The Project received environmental approval on 7 April 2025, subject to conditions designed to protect the environment and nearby sensitive areas. Environmental management measures, including water quality monitoring, will be implemented during construction. Since November, water quality monitoring buoys have been deployed in the waters surrounding the Pier, collecting data for establishing a baseline for monitoring quality during dredging operations.
The Public Environment Report and supporting documentation are available below:
-
DocumentPublic Environment Report (7.38 MB)
-
DocumentPublic Environment Report Appendices A-C (17.35 MB)
-
DocumentPublic Environment Report Appendices D-E (17.29 MB)
-
DocumentPublic Environment Report Appendices F-I (15.89 MB)
-
DocumentPublic Environment Report Appendices J-O (11.85 MB)
Planning approvals
A development application for the transport of dredged material to and associated restoration works at Cascade Quarry was approved in 2022 by the Norfolk Island Regional Council under the Planning Act 2002 (NI). The DA was amended in 2025 to include the associated Kingston Pier rock revetment remediation and extension project.
Project timing
Prior to commencement of dredging works, repairs and extension works to the Kingston Pier rock revetment will be undertaken to strengthen the structure and prepare it for the anticipated changes in wave action associated with the deeper navigation channel.
Land and Marine Ocean Engineering has been engaged to deliver the Kingston Pier Rock Revetment Repair project and is expected to commence construction during the week beginning 24 August 2026. The works will involve repairs to, and extension of, the existing rock revetment on the western side of Kingston Pier. These upgrades are required to respond to the expected changes in wave action resulting from the deeper channel that will be created as part of the Kingston Pier Channel Construction Project.
During construction, the area surrounding the existing rock revetment will be closed to public access and secured with temporary fencing. The community can also expect increased truck movements transporting rock armour from Youngs Road Quarry, Cascade, to Kingston Pier via Cascade Road and Middlegate Road, as well as construction machinery operating within the fenced work area.
The rock revetment works are expected to take approximately three months to complete, subject to weather and site conditions.
Procurement of a construction contractor for the dredging and repair of the Pier is planned for the second half of 2026. Once ready to commence, construction is expected to take approximately six to nine months to complete. The dredging component is anticipated to take around three months within this timeframe. Disruption to existing port operations during construction will be minimised as far as possible.
Further information
If you have questions about the Kingston Pier Channel Construction Project, please contact: