Alice Springs Airport

Site Investigation

  • Aurecon Australasia Pty Ltd (with Senversa) is the contaminated land specialist leading the Program Investigation at Alice Springs Airport.
  • Procurement of an accredited site auditor is currently underway.
  • The Program investigation at Alice Springs Airport commenced on 13 June 2025.
  • The investigation will examine potential sources of PFAS contamination at the airport, as well as potential migration pathways to receptors both on- and off- the airport site.
  • The Department is consulting with Airservices Australia to understand the scope of works already underway and to avoid duplication, where possible.
  • The Department is engaging with relevant state agencies to support the review of key investigation reports and plans.
  • Participation in the Program is voluntary. Alice Springs Airport formalised its involvement by signing a Memorandum of Understanding with the Department on 06 June 2025.

Where is the Investigation up to?

  • Lead consultants are currently collating site information and drafting the preliminary site investigation report.

Next Steps

  • The preliminary site investigation, and further investigations if required, will inform the development of a PFAS Management Plan for Alice Springs Airport that will document the approach to managing risks associated with PFAS contamination at the airport.

Additional Information

Contact Information

Last updated 10 November 2025