The Federal election was called on 10 April. As this website is hosted by the Department of Infrastructure, Transport, Regional Development and Communications, the site will only be updated with material in line with the Caretaker Conventions. Please note that the content of this site relates to the Australian Government’s existing policy.

Coronavirus (COVID-19) updates from the Australian Government

Townsville city deal

The Townsville City Deal is a 15 year commitment between the Australian and Queensland Governments and the Townsville City Council to a collective program of planning, reform and investment for Townsville. The commitments made under the City Deal are consistent with the Memorandum of Understanding between the Commonwealth and the State of Queensland to establish and implement City Deals, which was agreed on 10 November 2016.

Image
townsville-banner2

The Townsville City Deal was signed on 9 December 2016.  It outlines a series of commitments that all three tiers of government will work together to deliver, as well as a series of future opportunities for further collaboration, to deliver a transformational impact for Townsville.

The Townsville City Deal is a 15-year commitment that aims to support a prosperous economic future for Townsville. It will position Townsville as a vibrant, livable and innovative city in Northern Australia.

Key achievements

Key achievements of the Townsville City Deal in 2020 include:

  • Opening of the stadium officially named the Queensland Country Bank Stadium, with a concert by Sir Elton John on 29 February 2020 and the North Queensland Cowboys’ first match of the 2020 NRL season on 13 March 2020.
  • Construction of the Port of Townsville channel upgrade progressed with over 750,000 tonnes of rock used to build a 2.2km seawall (with dredging to commence later in 2021).
  • Completion of Stage 1 of the Haughton Pipeline from the Ross River Dam to the Haughton River, ready for eventual connection to Stage 2 between the Haughton and Burdekin Rivers.
  • Finalisation of the Townsville Health and Knowledge Development Strategy and the Townsville Workforce Development Plan, as well as the launch of TropiQ.
  • Launch of Smart Precinct NQ - an initiative of the Townsville Smart City Strategy.

2020 Annual Progress Report

The year 2020 was one of significant achievement for the Townsville City Deal, but also a time of extraordinary challenges in Australia and around the world. The COVID-19 pandemic has severely disrupted the global economy - causing business devastation, interrupting supply chains and forcing millions out of work. The North Queensland economy has not been spared these impacts, and the people of Townsville - still recovering from the 2019 monsoon event - have taken a hit.

Despite these challenges, a number of commitments under the Townsville City Deal were completed in 2020, adding to a growing list of successes over the past four years. In 2021, the economic momentum delivered by the Deal will be more important than ever in supporting Townsville to recover and prosper.

Timeline

  • Announcement of Townsville City Deal
    13 June 2016
  • Signing of Memorandum of Understanding for City Deals in Queensland
    Within six months
  • Signing of Townsville City Deal
    9 December 2016
  • Implementation Plan
    April 2017
  • First Annual Progress Report
    March 2018
  • Second Annual Progress Report
    April 2019
  • Third Annual Progress Report
    February 2020
  • Fourth Annual Progress Report
    January 2022
  • Formal Review of the Townsville City Deal
    January 2022
  • End of 15 years of Townsville City Deal
    2031

Download reports

Haughton Pipeline Stage 2